Air Utilities arranges and installs temporary builders supply, safe, metered electricity and water connections that power your construction site from day one, across England. Before a permanent connection is in place, your site still needs power for tools, machinery, lighting, site offices and welfare, and water for the works. We manage the whole temporary supply, from assessing your load and coordinating the Distribution Network Operator and supplier, through installing the metered connection, to converting it into your permanent supply or decommissioning it when the build is done.
A temporary builders supply (TBS) is an on-site, metered connection that provides electricity and, where needed, water to a construction site before the permanent connection is available. It powers everything a live site depends on: hand tools and machinery, site lighting, site cabins and offices, welfare facilities, and generators.
A temporary supply is typically used for up to 12 months. If power is needed beyond that, a permanent connection is required instead. Crucially, taking a temporary supply does not commit you to a permanent one, and it can be decommissioned when the works finish or, more efficiently, converted into the permanent connection the finished development needs.
You typically need a temporary builders supply when:
Getting the temporary supply in early keeps the build moving while the permanent connection is designed and delivered in the background.
The right temporary supply depends on the size of your site and what it has to run. Supplies split broadly by capacity, with 70 kVA the usual dividing line.
| Supply | Capacity | Suited to |
|---|---|---|
| Single-phase (30 to 32A) | Up to around 70 kVA | Housing and small commercial sites, tools, lighting, cabins |
| Three-phase (60 to 63A) | 70 kVA and above | Larger commercial and industrial sites, heavy machinery |
Smaller sites running basic tools, lighting and a site office are usually single-phase. Larger developments with multiple units, heavy plant and multiple site offices need a three-phase supply, and above 70 kVA the process also requires a meter operator (MOP) contract, which we arrange as part of the service.
One of the biggest advantages of arranging your temporary supply with a provider that also delivers permanent connections is what happens at the end. When the build completes, your temporary builders supply can either be:
Because Air Utilities delivers both, we plan the temporary supply with the permanent connection in mind from the start, so you are not paying twice for work that could have been done once.
To get your temporary supply moving quickly, it helps to have:
Where the load is not yet clear, we assess it for you and recommend the right supply configuration.
Timescales depend on whether there is existing infrastructure nearby and how much work the network operator has to do. As a general industry guide, a straightforward temporary supply where the network is close can be arranged in a few weeks, while sites that need new cabling or a longer connection to reach the network take longer. Because the temporary supply often sits on the critical path at the very start of a build, it is worth arranging as early as possible. We start the DNO and supplier coordination straight away so power is on site when your programme needs it.
We review the site, evaluate the load and determine the right temporary supply configuration.
We prepare and submit the applications, coordinating with the DNO and supplier to secure approvals and the MPAN.
We arrange the temporary supply contract and, for larger supplies, the meter operator (MOP) contract.
We install the metered connection, cabling and secure supply housing.
We connect and test the supply, support any capacity changes during the build, and convert or decommission it on completion.
A temporary builders supply is an on-site, metered electricity and, where needed, water connection that powers a construction site before the permanent connection is available. It runs tools, machinery, lighting, site offices and welfare facilities.
A temporary builders supply is typically used for up to 12 months. If power is needed beyond that, a permanent connection is required. The supply can be decommissioned or converted to permanent when the works finish.
Housing and smaller commercial sites are usually single-phase (30 to 32A, up to around 70 kVA). Larger commercial and industrial sites with heavy machinery need three-phase (60 to 63A, 70 kVA and above). We size the supply against your site's load.
No. A temporary supply does not commit you to a permanent connection. You can decommission it when the works finish, or convert it into the permanent supply if the development needs one, whichever is more cost-effective.
Yes, and it is often the most efficient route. Because Air Utilities delivers permanent connections too, we plan the temporary supply with conversion in mind, which can save both time and cost against arranging a permanent connection separately.
Yes. We arrange temporary water connections for site works and welfare alongside temporary electricity, so your site has both from one provider.
Tell us about your site and what you need to power, and we will arrange a safe, metered temporary supply and manage it through to conversion or decommissioning. Electricity and water, from application to switch-on.