Air Utilities upgrades properties from single-phase to three-phase power across England, for homes and businesses that have outgrown their existing supply. A three-phase supply gives you roughly three times the capacity, which is what you need to run heavy or stacked loads such as a large heat pump, a 22kW EV charger, workshop machinery or a commercial kitchen without tripping the supply. We assess whether you genuinely need three-phase or whether a simpler upgrade will do, handle the DNO application, and manage the whole connection through to a live supply.
Most UK homes and small premises have a single-phase supply: one live conductor at 230V, usually with a 60A to 100A fuse, giving roughly 14 to 23 kVA of capacity at any one time. That is plenty for a normal household.
A three-phase supply provides three live conductors at 400V between phases, giving around three times the power over the same incoming connection. It is the standard for commercial and industrial premises, and increasingly relevant for homes adding several high-power electric loads at once.
| Single-phase | Three-phase | |
|---|---|---|
| Voltage | 230V | 400V between phases |
| Typical capacity | 14 to 23 kVA (60 to 100A) | Around three times single-phase |
| Standard for | Homes, small units | Commercial, industrial, high-load homes |
You should consider three-phase when your total demand pushes past what a single-phase supply can comfortably deliver, typically around 100A after diversity, or when you are adding specific heavy loads:
If your existing single-phase supply trips under load, or cannot support what you want to add, that is the clearest signal to assess a three-phase upgrade.
Three-phase is not always the right answer, and it can cost thousands. Before recommending it, we check whether a simpler, cheaper option gives you the capacity you need. In many cases, upgrading a single-phase supply from a 60A to an 80A or 100A fuse, or upgrading the consumer unit, provides enough extra headroom at a fraction of the cost of a full three-phase conversion.
We assess your total demand first and give you an honest recommendation, because the cheapest solution that meets your needs is usually the right one. We would rather tell you a board upgrade will do than sell you a conversion you do not need.
A three-phase upgrade is more than a meter swap. Once the DNO approves the application, the process usually involves:
The DNO excavates to expose and replace your existing single-phase supply cable with a three-phase one, which typically means digging up part of a garden, driveway or, in some cases, a footpath or road.
A new three-phase consumer unit or distribution board is fitted internally.
Circuits are rewired and connected for the loads that need three-phase.
The energy supplier changes the meter to a three-phase unit.
Loads are balanced as evenly as possible across the three phases at commissioning.
The groundworks, particularly where a road or shared driveway is involved, are usually the biggest cost and time driver.
Because every property and its distance from the network is different, we do not publish fixed prices. Tell us about your property and what you want to power, and we will arrange the DNO quote and give you an accurate, no-obligation cost.
As a general industry guide, a straightforward upgrade where three-phase is already close can be completed in a matter of weeks once the DNO application is approved, while jobs that need new cable, extensive groundworks or network reinforcement take longer. The DNO application and any network works are the main variable, so the earlier the application goes in, the sooner the upgrade completes. We submit and manage the DNO side straight away to keep the timeline as short as possible.
We confirm whether you need three-phase or whether a simpler supply or board upgrade will do.
We apply to the DNO for the three-phase supply and obtain the quote.
The single-phase cable is replaced with three-phase, including excavation and reinstatement.
We install the three-phase board, rewire the relevant circuits and coordinate the meter change.
We balance the load across the phases, test, certify and energise the supply.
Only for a 22kW charger. A standard 7kW home charger runs perfectly well on a single-phase supply. Most homes only need three-phase if they are adding several heavy loads together, not for EV charging alone.
Often for larger units. Industry guidance suggests heat pumps above around 8kW (roughly 32A per phase) are likely to need three-phase, but smaller units usually run on single-phase. We assess your specific unit against your existing supply.
Frequently, yes. Upgrading from a 60A to an 80A or 100A single-phase supply, or upgrading the consumer unit, can give enough extra capacity at a fraction of the cost of a full three-phase conversion. We check this before recommending three-phase.
Yes. A three-phase upgrade requires a supply upgrade application to your Distribution Network Operator, and we manage that whole process for you, including obtaining the quote and coordinating the works.
The unit price of electricity is the same. Three-phase does not make your energy more expensive to run; it simply gives you more capacity. The cost is in the upgrade itself, not the running.
Possibly. If a new three-phase cable is needed, the DNO excavates to replace the existing supply cable, which can mean digging up part of a garden, driveway, footpath or road. We confirm the likely route and reinstatement as part of the assessment.
Tell us about your property and what you want to power, and we will confirm whether you need three-phase, handle the DNO application, and manage the upgrade through to a live supply.